MORE EV charging points will be rolled out on Bradford streets after extra funding was awarded to the region.
At a meeting of West Yorkshire Combined Authority (WYCA) on Thursday, members were told that a regionwide scheme to bring charging points to areas where few households have access to off street parking was getting extra public money.
Originally Bradford was due to get £282,000 to create scores of new EV points across the district.
But a report to WYCA revealed that this had now increased to £357,881.
Why has the funding increased?
The Local Electric Vehicle Infrastructure (LEVI) Capability Scheme was a project that used both public cash and private sector investment to boost the region’s charging infrastructure.
It would “prioritise high-density housing areas without off-street parking” to allow more people to switch to EV vehicles.
Currently there are few options for people who rely on on street parking, which often isn’t directly in front of their homes, to charge their electric vehicles unless they use pricier commercial charging stations.
Originally the LEVI scheme would have used £1,502,709 of Government money.
But the report to WYCA said Government had now awarded an additional £539,560.
How much will each West Yorkshire council get?
It said the bulk of the extra funding would go to the five council areas in West Yorkshire, and the share for each council area was now:
- Bradford Council up to £357,881
- Calderdale Council up to £347,217
- Kirklees Council up to £332,903
- Leeds City Council up to £305,848
- Wakefield Council up to £342,634
Scheme to deliver 716 EV charging points
The report said: “Due to the success of the Phase 1 procurement, the number of charging points the scheme will deliver has increased from 232 to 716.
“This is as a result of the procured supplier offering a 58 per cent private sector contribution to the scheme costs, which was significantly higher than the 38 per cent anticipated following market testing prior to procurement.
“This success has led to partner councils needing to undertake additional work before entering into contracts, for example increases in site leases / licenses, site assessments and approvals, for the additional charging points.
“Partner councils therefore need more resources to manage their contracts.
“The Phase 1 procurement took longer than expected, with partner councils entering into contracts from July to September 2025 instead of the target date of April 2025.”
Members voted to extend the timeframe to deliver the new charging points from June 2026 to April 2028.