A MAJOR £30m project to improve Bradford’s electricity network is moving into its final stages.

The work, which Northern Powergrid started in September 2019, has focused on replacing five major circuits.

The work is being done to ensure the electricity network can meet the existing demand for power, as well as future increases in demand.

Bradford Telegraph and Argus: Northern Powergrid Northern Powergrid (Image: Northern Powergrid)

It has involved laying around 87 miles of new underground electricity cables with a route length of 10.5 miles through Wilsden, Thornton, Allerton, Fairweather Green, Four Lane Ends, Girlington, Sandy Lane, Heaton, Manningham and the city centre.

Between early October 2022 and the end of May 2023, Northern Powergrid will be carrying out some small roadworks at several locations to remove redundant equipment associated with the old electricity network.

Temporary multi-way traffic lights will be in place for up to five days at each of the following locations, with some areas requiring follow-up work which will also take approximately five to seven days to complete:

Back Lane, Wilsden, near the junction of Back Lane

Early October 2022

Early February 2023                                                                                          

Wilsden Road between the junctions of Shay Lane and Prune Park Lane

Mid-October 2022

Queen’s Road railway bridge

Mid-end October 2022

Mid-end January 2023                                                                                                              

Junction of Wilsden Road, Cottingley Road, Stony Lane

October half-term 2022

Back Lane at various locations between the junctions of Old Allen Road and Wilsden Road

Early November 2022

End of February 2023

Wilsden Road, between the junction of Prune Park Lane and the Wilsden Road/Cottingley Road/Stony Lane crossroads                                                                      

Mid-end November 2022

End of February/early March 2023

Haworth Road, near to the Bay of Biscay houses

End of September/early October 2022

Haworth Road at the junction of Heather Grove

Early December 2022

Early to mid-March 2023

Haworth Road near the junction of Chellow Grange Road/Brantwood Drive

Early December 2022

Scotchman Road at the junction of Graham Street and also opposite Manningham Concrete

December 2022 (during school holidays to reduce disruption)                 

Haworth Road at the junction of Thorn Lane

Early December 2022

Mid-end March 2023

Haworth Road at the junction of Heights Lane

Early January 2023

Toller Lane, near the junction of Toller Drive

Early-mid January 2023

Toller Lane, near the junction of Heaton Park Drive

Mid-end January 2023

End-March/early April 2023

North Avenue

October half-term (October 21-25 2022)

Mid-end March 2023

Queen’s Road at the junction of Station Road

Early October 2022                                                                               

Sharon Incerti, Northern Powergrid Project Engineer, said: “These final small pieces of work will bring to an end our three-and-a-half-year programme to deliver £30 million investment in Bradford’s electricity network.”