Yorkshire Water is continuing its £1.3 million project to improve the quality of the water supply in South Craven.
Next week's work schedule is: Dixon Street (Sutton), November 12; Green Lane (Glusburn), November 12 and 13; rear of Main Street (Cross Hills), November 12 and 13; Holmroyd Avenue (Cross Hills), November 13 to 15; Ravenstone Gardens (Sutton), November 15 and 16; Harker Street (Sutton), November 16; Mill Street (Sutton), November 19; North Street (Sutton), November 19; Holly Bank (Sutton), November 7 to 14; and rear of St Andrew's Terrace (Cross Hills), November 15 to 19.